Guide · updated October 12, 2026
Ksi Lisims LNG: status, offtake, contractors and FID timing (2026)
The Nisga’a Nation-led Ksi Lisims LNG project and its Prince Rupert Gas Transmission line: how much of the 12 Mtpa is sold, who has the pipeline contracts, cost and the final investment decision timeline.
Ksi Lisims LNG is a floating 12 Mtpa export project on Nisga’a lands near the Alaska border. It is owned by the Nisga’a Nation, Rockies LNG and Western LNG. On September 30, 2026, Centrica signed a heads of agreement for 1 Mtpa over 20 years, bringing announced offtake to about 9 of 12 Mtpa. A final investment decision is targeted by the end of 2026, with construction as early as 2027 if approved. Gas would come through the Prince Rupert Gas Transmission (PRGT) line. Surerus Murphy JV holds the onshore work and Allseas the subsea section.
For suppliers, the PRGT spreads and the shore-side works are where Canadian contractors will find most of the early work.
In this guide
- LNG Canada Phase 2
- Coastal GasLink Phase 2
- Cedar LNG
- Ksi Lisims LNG + Prince Rupert Gas Transmission (PRGT)
- North Coast Transmission Line (NCTL)
LNG Canada Phase 2
British Columbia · LNG · Kitimat
LNG Canada Phase 2 starts early works three days after its investment decision.
- Status: FID Sep 28, 2026; early works since Oct 1
- Next: ~4 months of early works, then full construction
- Disclosed cost: ~C$33B private investment (federal estimate)
- Owner: LNG Canada JV: Shell, PETRONAS, PetroChina, Mitsubishi, KOGAS; Contractors: JGC Fluor BC LNG II JV
Sources:
Coastal GasLink Phase 2
British Columbia · Pipeline · Dawson Creek–Kitimat
Coastal GasLink Phase 2 is a compressor-station job, not a pipeline spread.
- Status: Proceeding; conditions met Sep 29
- Next: Construction early 2027; in service early 2030s
- Disclosed cost: Not publicly disclosed
- Owner: Coastal GasLink; operated by TC Energy; Contractors: LNG Canada (Phase 2 Execution Manager)
- In service: Early 2030s
Sources:
Cedar LNG
British Columbia · LNG · Kitimat
Cedar LNG: site crews hand over as the floating plant takes shape in Korea.
- Status: Pipeline welded; FLNG >50%
- Next: Ledcor handover Oct 2026; startup late 2028
- Disclosed cost: US$4.0B total (US$3.4B capital)
- Owner: Haisla Nation and Pembina; Contractors: Ledcor Haisla LP; FLNG by Samsung Heavy Industries
- In service: Late 2028
Sources:
Ksi Lisims LNG + Prince Rupert Gas Transmission (PRGT)
British Columbia · LNG + pipeline · North Coast
Ksi Lisims has 9 of 12 Mtpa lined up as its FID deadline nears.
- Status: Pre-FID
- Next: FID targeted by end-2026; construction early 2027 if approved
- Disclosed cost: C$30B facility (federal 2026 figure) + C$10–12B PRGT
- Owner: Nisga'a Nation, Rockies LNG, Western LNG; Contractors: PRGT: Surerus Murphy JV (onshore), Allseas (subsea)
- In service: 2032 (first Uniper deliveries)
Sources:
North Coast Transmission Line (NCTL)
British Columbia · Power · Prince George–Terrace
North Coast Transmission Line: the region's clearest procurement calendar.
- Status: Phase 1 clearing since July; four line teams shortlisted
- Next: Oct 15 final draft contract · Dec 15 proposals · May 2027 award
- Disclosed cost: C$6B (Phases 1–2, BC Hydro estimate); C$3.9B federal–provincial commitment
- Owner: BC Hydro (500 kV)
- In service: 2032–2034 (phased)
Sources:
Frequently asked
Has Ksi Lisims LNG reached FID?
Not as of our October 2026 update. The project is targeting a final investment decision by the end of 2026.
Who is building the Prince Rupert Gas Transmission pipeline?
Surerus Murphy JV has the onshore work and Allseas the subsea section, according to contract-award reporting cited on our project page.
The full brief is in the October 2026 report: the procurement packages to watch, the buyer and contractor contacts, the dates on the 90-day calendar and how this project ties into the rest of the pipeline.