Week of October 12, 2026
| When | Type | Project | What happens | Buyer |
|---|---|---|---|---|
| Oct 13–16 | Construction | Fall oil sands and refinery turnarounds | Suncor and Syncrude fall turnarounds scheduled to finish | Suncor; Syncrude |
| Oct 15 | Tender / RFP | North Coast Transmission Line (NCTL) | Prince George–Glenannan final draft contract issued to the four shortlisted line teams | BC Hydro |
| Oct 15 | Regulatory | Cenovus Christina Lake interconnect | AER statement-of-concern deadline | Cenovus / AER |
| Oct 24 | Policy | Policy and market | B.C. general election; BC Hydro Call for Demand results follow the transition | Province of B.C. |
Next after that
| When | Type | Project | What happens | Buyer |
|---|---|---|---|---|
| Oct 2026 | Award | North Coast Transmission Line (NCTL) | Subscribers only | BC Hydro |
| Oct 2026 | Construction | Cedar LNG | Subscribers only | Cedar LNG Partners |
| Oct 2026 | Construction | Eagle Mountain–Woodfibre Gas Pipeline (EGP) | Subscribers only | FortisBC |
| Late Nov 2026 | Construction | Red Chris block cave and Eskay Creek | Subscribers only | Skeena Gold + Silver |
| Nov 2026 | Award | North Coast Transmission Line (NCTL) | Subscribers only | BC Hydro |
| Nov 2026 | Construction | Seabridge KSM copper-gold project | Subscribers only | Seabridge Gold / BC Hydro |
Where the biggest projects stand
- LNG Canada Phase 2: FID Sep 28, 2026; early works since Oct 1
- Coastal GasLink Phase 2: Proceeding; conditions met Sep 29
- Cedar LNG: Pipeline welded; FLNG >50%
- Ksi Lisims LNG + Prince Rupert Gas Transmission (PRGT): Pre-FID
- Woodfibre LNG: ~65% complete
- North Coast Transmission Line (NCTL): Phase 1 clearing since July; four line teams shortlisted
- Tilbury Phase 2 LNG: B.C. EA certificate and federal decision, both Sep 21
- Red Chris block cave and Eskay Creek:
What subscribers see that this page doesn’t show
| What you get | Free | Paid |
|---|---|---|
| Project list with owner, status, next milestone and cost | ✓ | ✓ |
| Next 10 dates on the bid calendar | ✓ | ✓ |
| All 64 dated milestones, .ics export and a watchlist | — | ✓ |
| What happens on each date (details for every milestone) | — | ✓ |
| Procurement packages and buyer contacts per project | — | ✓ |
| Two monthly reports (PDF) with maps and buyer tables | — | ✓ |
| Mid-month update on projects that moved | — | ✓ |
Upgrade now: C$299/yr or C$39 a month
Opens secure checkout (card, Apple Pay, Google Pay, Link). Cancel any time in two clicks.