Western Canada major projects tracker
The 22 industrial, energy and data-centre projects we track in British Columbia, Alberta and Saskatchewan: owner, status, next milestone and disclosed cost. Click a project for its contractors, schedule and sources.
| Project | Province | Sector | Status | Next milestone | Disclosed cost |
|---|---|---|---|---|---|
| LNG Canada Phase 2 | B.C. | LNG | FID Sep 28, 2026; early works since Oct 1 | ~4 months of early works, then full construction | ~C$33B private investment (federal estimate) |
| Coastal GasLink Phase 2 | B.C. | Pipeline | Proceeding; conditions met Sep 29 | Construction early 2027; in service early 2030s | — |
| Cedar LNG | B.C. | LNG | Pipeline welded; FLNG >50% | Ledcor handover Oct 2026; startup late 2028 | US$4.0B total (US$3.4B capital) |
| Ksi Lisims LNG + Prince Rupert Gas Transmission (PRGT) | B.C. | LNG + pipeline | Pre-FID | FID targeted by end-2026; construction early 2027 if approved | C$30B facility (federal 2026 figure) + C$10–12B PRGT |
| Woodfibre LNG | B.C. | LNG | ~65% complete | Pipe installation in tunnel; first cargo targeted Dec 2027 | US$8.8B |
| North Coast Transmission Line (NCTL) | B.C. | Power | Phase 1 clearing since July; four line teams shortlisted | Oct 15 final draft contract · Dec 15 proposals · May 2027 award | C$6B (Phases 1–2, BC Hydro estimate); C$3.9B federal–provincial commitment |
| Tilbury Phase 2 LNG | B.C. | LNG | B.C. EA certificate and federal decision, both Sep 21 | Remaining permits; owner investment decision | C$3.1B (FortisBC projection) |
| Red Chris block cave and Eskay Creek | B.C. | Mining | — | Red Chris FID later this year · Eskay power late Nov, first ore Q2 2027 | Red Chris ~C$3B (Newmont); Eskay Creek US$659M (2026 update) |
| Pacific Link oil pipeline | Alberta | Pipeline | Listed Oct 1 under the Building Canada Act | MPO conditions document; earliest start Sep 1, 2027 | C$35.2–43.7B (preliminary, incl. contingency) |
| Dow Path2Zero | Alberta | Petrochemical | Construction proceeding after the 2025 pause | Phase 1 late 2029; Phase 2 end of 2030 | ~US$7.5B |
| Cenovus Christina Lake interconnect | Alberta | Oil sands | AER notice Sep 15 | Statement-of-concern deadline Oct 15; construction mid-2027; startup Q4 2028 | — |
| Fall oil sands and refinery turnarounds | Alberta | Turnarounds | — | Spring 2027 turnaround planning | — |
| Alliance Heartland Expansion and Pathways CCS | Alberta | Gas pipeline + CCS | — | Alliance construction Apr 2028–Sep 2030 (CER page) | Alliance not disclosed; Pathways phase 1 C$20–30B (reported) |
| BHP Jansen potash mine | Saskatchewan | Mining | Stage 1 84% complete · Stage 2 16% | First production mid-calendar 2027 | Stage 1 US$8.4B; Stage 2 US$6.9B |
| Meta data centre, Sturgeon County | Alberta | Data centre | Ground broken Jul 8, 2026 | Load in service back half of 2028 | >C$13B |
| Greenlight Electricity Centre | Alberta | Gas power | FID Jul 2; all major approvals in hand | In service H2 2030 | ~C$4.6B incl. financing |
| Capital Power supply to Meta / Genesee | Alberta | Power supply | — | Load in back half of 2028 | — |
| Keephills data centre (TransAlta) | Alberta | Data centre | Non-binding MOU, Feb 27, 2026 | Definitive agreements and a ~230 MW PPA | — |
| Beacon AI Centers (Heartland and Indus) | Alberta | Data centre + gas | — | AUC decisions | Up to US$7.2B across the Alberta portfolio |
| Wonder Valley data centre | Alberta | Data centre | Proposed; EPEA and Water Act approvals outstanding | Permit applications and decisions | Proponent claims ~C$70B at full build |
| Bell AI Fabric Hillside AI Centre, Kamloops | B.C. | Data centre | Construction since spring 2026 | Completion late 2027 | — |
| Bell AI Fabric, Regina area | Saskatchewan | Data centre + gas | 300 MW under construction (RM of Sherwood); +900 MW non-binding MOU | Tenant commitments, a power partner, EAs | ~C$1.7B for the 300 MW phase; >C$50B for the 1.2 GW expansion (provincial figure) |
Costs as published by the owner or government, in the currency published. “—” means no figure has been released. Research cut-off October 12, 2026.
Browse by province
British Columbia (9)Alberta (11)Saskatchewan (2)
Browse by sector
LNG (5)Pipelines (3)Power and transmission (3)Data centres (6)Mining (2)Oil sands and petrochemicals (3)
Policy, grid and market context this month
- B.C. provincial election (Oct 24): The election pause: B.C. votes Oct 24.
- AESO large-load integration: Large-load integration: Phase 1 is full, Phase 2 is still on hold.
- Alberta data-centre levy (Bill 12): The data-centre levy (Bill 12) applies from Dec 31, 2026.
- Bill impact of bridging load (Pembina Institute): Pembina Institute: bridging load could raise Alberta bills.
- BC Hydro 2026 Call for Demand: 2026 Call for Demand: about 2:1 oversubscribed and paused for the election.
The full brief is in the October 2026 report: the procurement packages to watch, the buyer and contractor contacts, the dates on the 90-day calendar and how this project ties into the rest of the pipeline.