Data-centre projects in Western Canada

9 tracked projects. AI and hyperscale data centres in Alberta, B.C. and Saskatchewan, and the behind-the-meter power behind them.

ProjectProvinceSectorStatusNext milestoneDisclosed cost
Meta data centre, Sturgeon CountyAlbertaData centreGround broken Jul 8, 2026Load in service back half of 2028>C$13B
Keephills data centre (TransAlta)AlbertaData centreNon-binding MOU, Feb 27, 2026Definitive agreements and a ~230 MW PPA—
Beacon AI Centers (Heartland and Indus)AlbertaData centre + gas—AUC decisionsUp to US$7.2B across the Alberta portfolio
Wonder Valley data centreAlbertaData centreProposed; EPEA and Water Act approvals outstandingPermit applications and decisionsProponent claims ~C$70B at full build
Bell AI Fabric Hillside AI Centre, KamloopsB.C.Data centreConstruction since spring 2026Completion late 2027—
Bell AI Fabric, Regina areaSaskatchewanData centre + gas300 MW under construction (RM of Sherwood); +900 MW non-binding MOUTenant commitments, a power partner, EAs~C$1.7B for the 300 MW phase; >C$50B for the 1.2 GW expansion (provincial figure)
eStruxture CAL-3 data centreAlbertaData centreUnder construction (Alberta Major Projects, 2024–2026)Phase 1 online in 2026C$750M (Alberta Major Projects)
TNE / Data District data centres (Phase 1)AlbertaData centreProposed (Alberta Major Projects)Olds construction 2026; Bonnyville 2027C$1.26B (four sites)
Crusoe AI data centres with Kalina gas powerAlbertaData centreProposed (Alberta Major Projects)Power plant and site approvalsC$3B (about C$1B per 170 MW plant)