Free tool · updated October 12, 2026

Western Canada data centre and power pipeline map

9 data-centre projects and 7 power and transmission projects in Alberta, B.C. and Saskatchewan. Red dots are data centres, yellow dots are power. Tap a dot for the project page.

Map of data-centre and power projects in B.C., Alberta and Saskatchewan
  • Data centres (9)
  • Power and transmission (7)

Disclosed Canadian-dollar cost on this map: C$46B+.

Get Data Centre & Energy Watch

Data centres

ProjectProvinceOwnerContractorsStatusNext milestoneDisclosed cost
Meta data centre, Sturgeon CountyAlbertaMeta Platforms—Ground broken Jul 8, 2026Load in service back half of 2028>C$13B
Keephills data centre (TransAlta)AlbertaTransAlta (site and power) · CPP Investments and Brookfield—Non-binding MOU, Feb 27, 2026Definitive agreements and a ~230 MW PPANot publicly disclosed
Beacon AI Centers (Heartland and Indus)Alberta———AUC decisionsUp to US$7.2B across the Alberta portfolio
Wonder Valley data centreAlberta——Proposed; EPEA and Water Act approvals outstandingPermit applications and decisionsProponent claims ~C$70B at full build
Bell AI Fabric Hillside AI Centre, KamloopsB.C.Bell AI Fabric (with TRU Community Trust)—Construction since spring 2026Completion late 2027Not publicly disclosed
Bell AI Fabric, Regina areaSaskatchewanBell Canada—300 MW under construction (RM of Sherwood); +900 MW non-binding MOUTenant commitments, a power partner, EAs~C$1.7B for the 300 MW phase; >C$50B for the 1.2 GW expansion (provincial figure)
eStruxture CAL-3 data centreAlbertaeStruxture—Under construction (Alberta Major Projects, 2024–2026)Phase 1 online in 2026C$750M (Alberta Major Projects)
TNE / Data District data centres (Phase 1)AlbertaTechnologies New Energy and Data District—Proposed (Alberta Major Projects)Olds construction 2026; Bonnyville 2027C$1.26B (four sites)
Crusoe AI data centres with Kalina gas powerAlbertaCrusoe (power: Kalina Distributed Power)—Proposed (Alberta Major Projects)Power plant and site approvalsC$3B (about C$1B per 170 MW plant)

Power and transmission

ProjectProvinceOwnerContractorsStatusNext milestoneDisclosed cost
North Coast Transmission Line (NCTL)B.C.BC Hydro (500 kV)—Phase 1 clearing since July; four line teams shortlistedOct 15 final draft contract · Dec 15 proposals · May 2027 awardC$6B (Phases 1–2, BC Hydro estimate); C$3.9B federal–provincial commitment
Greenlight Electricity CentreAlbertaPembina 47.5% · Morgan Stanley Infrastructure 47.5% · Kineticor 5%Aecon + Técnicas Reunidas (fixed price) · Siemens EnergyFID Jul 2; all major approvals in handIn service H2 2030~C$4.6B incl. financing
Capital Power supply to Meta / GeneseeAlbertaMeta Platforms——Load in back half of 2028Not publicly disclosed
SaskPower Aspen Power StationSaskatchewanSaskPowerBurns & McDonnell (EPC)Under construction since April 2024; 1.4M worker hours to dateCommissioning, then in service December 2027Not publicly disclosed
Site C Clean Energy ProjectB.C.BC Hydro—All six generating units in service by Aug 8, 2025; more than 94% complete overall (Mar 2026)Remaining works and close-out; about C$1.1B left to spendC$16B approved budget (C$14.9B spent to Mar 31, 2026)
BC Hydro 2024 and 2025 calls for powerB.C.BC Hydro (independent power producers)—2024 call: 10 EPAs (nine wind, one solar), about 4,830 GWh/yr. 2025 call: four projects, about 3,500 GWh/yr, announced May 2026Permitting; BC Hydro interconnection work from 2027; projects online from 2030–2033C$4.3B private investment (2025 call, Province)
BC Hydro Peace to Kelly Lake Stations SustainmentB.C.BC Hydro—Implementation phase (board-approved Dec 2022); no material changes in the Nov 2024–Oct 2025 reporting periodIn service October 2028C$354.0M authorized (BC Hydro)

What subscribers see that this page doesn’t show

What you getFreePaid
Project list with owner, status, next milestone and cost✓✓
Next 10 dates on the bid calendar✓✓
All 64 dated milestones, .ics export and a watchlist—✓
What happens on each date (details for every milestone)—✓
Procurement packages and buyer contacts per project—✓
Two monthly reports (PDF) with maps and buyer tables—✓
Mid-month update on projects that moved—✓

Upgrade now: C$299/yr or C$39 a month

Opens secure checkout (card, Apple Pay, Google Pay, Link). Cancel any time in two clicks.

Frequently asked

Which data centres are planned in Alberta?

Meta data centre, Sturgeon County, Keephills data centre (TransAlta), Beacon AI Centers (Heartland and Indus), Wonder Valley data centre, eStruxture CAL-3 data centre, TNE / Data District data centres (Phase 1), Crusoe AI data centres with Kalina gas power.

Where will the power for new data centres come from?

Behind-the-meter gas plants, grid connections and utility calls for power. The power projects on this map include North Coast Transmission Line (NCTL), Greenlight Electricity Centre, Capital Power supply to Meta / Genesee, SaskPower Aspen Power Station, Site C Clean Energy Project, BC Hydro 2024 and 2025 calls for power, BC Hydro Peace to Kelly Lake Stations Sustainment.

How often is the map updated?

With each monthly issue, and status changes go to subscribers in the mid-month update.