Sector · updated October 12, 2026
LNG projects in Western Canada
5 tracked projects. Liquefaction plants, export terminals and the contractor teams building them, from Kitimat to Squamish and the Fraser River.
| Project | Province | Sector | Status | Next milestone | Disclosed cost |
|---|---|---|---|---|---|
| LNG Canada Phase 2 | B.C. | LNG | FID Sep 28, 2026; early works since Oct 1 | ~4 months of early works, then full construction | ~C$33B private investment (federal estimate) |
| Cedar LNG | B.C. | LNG | Pipeline welded; FLNG >50% | Ledcor handover Oct 2026; startup late 2028 | US$4.0B total (US$3.4B capital) |
| Ksi Lisims LNG + Prince Rupert Gas Transmission (PRGT) | B.C. | LNG + pipeline | Pre-FID | FID targeted by end-2026; construction early 2027 if approved | C$30B facility (federal 2026 figure) + C$10–12B PRGT |
| Woodfibre LNG | B.C. | LNG | ~65% complete | Pipe installation in tunnel; first cargo targeted Dec 2027 | US$8.8B |
| Tilbury Phase 2 LNG | B.C. | LNG | B.C. EA certificate and federal decision, both Sep 21 | Remaining permits; owner investment decision | C$3.1B (FortisBC projection) |
The full brief is in the October 2026 report: the procurement packages to watch, the buyer and contractor contacts, the dates on the 90-day calendar and how this project ties into the rest of the pipeline.