Sector · updated October 12, 2026

Transit and infrastructure projects in Western Canada

7 tracked projects. SkyTrain and LRT lines, the Fraser River Tunnel and arena districts: the public-sector builds with the longest procurement calendars.

ProjectProvinceSectorStatusNext milestoneDisclosed cost
Surrey Langley SkyTrainB.C.TransitAll eight stations under construction (May 2026); C$2.8B spent to July 2026Initial testing from late 2026; construction along the corridor through 2029C$5.996B (provincial budget)
Broadway SubwayB.C.TransitAll trackwork complete (Sept 2026); dynamic train testing since May 2026Broadway fully reopens Jan 2027; trial running then opening in fall 2027Nearly C$3B (Province); B.C. C$1.957B, Canada C$896.9M, Vancouver C$100.3M in kind
Fraser River Tunnel (George Massey replacement)B.C.TransportationEarly works since Jan 2026; RFQs for first two packages issued June 16, 2026Package 1–2 contractors selected early 2027; remaining three packages procured in 2027; major construction 2027C$8.5B (Province); Canada up to C$3B
Calgary Green Line LRT (SE)AlbertaTransitSeven construction projects active; eight contracts worth more than C$200M awarded since June 2025Bow River and Shepard–Bow civil packages, track, comms and traction power, and signalling RFPs through 2026; station contracts later in 2026, built from 2027C$6.248B committed (three governments)
Valley Line West LRTAlbertaTransit68.7% complete at end of Q2 2026 (independent certifier); on budgetConstruction complete 2028, then testing and commissioningC$2.6B (City project budget)
Scotia Place event centreAlbertaBuildingsUnder construction since January 2025 (foundations first)Opening fall 2027C$926.4M initial investment (City, Province, CSEC partners)
Roberts Bank Terminal 2B.C.PortsPreferred proponent named July 2026; design and early-works agreement expected Q3 2026Design-build agreement expected Q1 2028, then construction; completion mid-2030s—

See all 50 tracked projects

The full brief is in the October 2026 report: the procurement packages to watch, the buyer and contractor contacts, the dates on the 90-day calendar and how this project ties into the rest of the pipeline.

Read it for C$299 a year or see a free sample