Transit and infrastructure projects in Western Canada
7 tracked projects. SkyTrain and LRT lines, the Fraser River Tunnel and arena districts: the public-sector builds with the longest procurement calendars.
| Project | Province | Sector | Status | Next milestone | Disclosed cost |
|---|---|---|---|---|---|
| Surrey Langley SkyTrain | B.C. | Transit | All eight stations under construction (May 2026); C$2.8B spent to July 2026 | Initial testing from late 2026; construction along the corridor through 2029 | C$5.996B (provincial budget) |
| Broadway Subway | B.C. | Transit | All trackwork complete (Sept 2026); dynamic train testing since May 2026 | Broadway fully reopens Jan 2027; trial running then opening in fall 2027 | Nearly C$3B (Province); B.C. C$1.957B, Canada C$896.9M, Vancouver C$100.3M in kind |
| Fraser River Tunnel (George Massey replacement) | B.C. | Transportation | Early works since Jan 2026; RFQs for first two packages issued June 16, 2026 | Package 1–2 contractors selected early 2027; remaining three packages procured in 2027; major construction 2027 | C$8.5B (Province); Canada up to C$3B |
| Calgary Green Line LRT (SE) | Alberta | Transit | Seven construction projects active; eight contracts worth more than C$200M awarded since June 2025 | Bow River and Shepard–Bow civil packages, track, comms and traction power, and signalling RFPs through 2026; station contracts later in 2026, built from 2027 | C$6.248B committed (three governments) |
| Valley Line West LRT | Alberta | Transit | 68.7% complete at end of Q2 2026 (independent certifier); on budget | Construction complete 2028, then testing and commissioning | C$2.6B (City project budget) |
| Scotia Place event centre | Alberta | Buildings | Under construction since January 2025 (foundations first) | Opening fall 2027 | C$926.4M initial investment (City, Province, CSEC partners) |
| Roberts Bank Terminal 2 | B.C. | Ports | Preferred proponent named July 2026; design and early-works agreement expected Q3 2026 | Design-build agreement expected Q1 2028, then construction; completion mid-2030s | — |
The full brief is in the October 2026 report: the procurement packages to watch, the buyer and contractor contacts, the dates on the 90-day calendar and how this project ties into the rest of the pipeline.