British Columbia · Transportation · updated October 12, 2026

Fraser River Tunnel (George Massey replacement)

A C$8.5B, eight-lane tunnel, re-tendered in five packages after the original agreement ended.

Bidding on work like this? Subscribers get the procurement packages, buyer contacts and 90-day calendar for 50 projects like Fraser River Tunnel (George Massey replacement), every month.

Get the full reports: C$299/yr Free: Top 25 projects PDF

Province
British Columbia
Location
Richmond–Delta (Highway 99)
Sector
Transportation
Owner
Province of B.C. (Ministry of Transportation and Transit)
EPC / contractors
Re-procuring; the Cross Fraser Partnership early-works agreement was terminated in 2026
Status
Early works since Jan 2026; RFQs for first two packages issued June 16, 2026
Next milestone
Package 1–2 contractors selected early 2027; remaining three packages procured in 2027; major construction 2027
Disclosed cost
C$8.5B (Province); Canada up to C$3B (source)
Construction start
Early works Jan 2026; major 2027
In service
September 2031
Other details
Environmental assessment review expected to finish by end of 2026

Why it matters for contractors and suppliers

Splitting the work into five packages opens primes and subcontracts to B.C.

and Canadian firms that could not have bid one mega-contract. Three of the packages are still to be tendered in 2027.

Want to know when Fraser River Tunnel (George Massey replacement) moves? Status changes, contract awards and tender dates for every tracked project go to subscribers in the mid-month update, alongside the two monthly reports.

Subscribe for C$299 a year or get the free Top 25 PDF

C$24.92 a month, billed yearly. Cancel any time in two clicks.

Free vs full reports

FreeFull reports
C$299/yr or C$39/mo
Project tracker: owner, status, next milestone, cost✓✓
Monthly front pages and headlines by email✓✓
Free Top 25 Projects one-pager✓✓
Both full monthly reports (21 pages in October 2026)–✓
Procurement packages and buyer and contractor contacts–✓
Bid calendar: tenders, awards and deadlines, exportable to Outlook or Google–✓
Project watchlist, highlighted in the mid-month update–✓
Mid-month update when tracked projects move–✓
Every past issue in your account–✓
Get the free PDFSubscribe

C$24.92 a month billed yearly (save 36%). Cancel any time in two clicks.

Sources

Supplier registration: owner supplier page · B.C. public tenders. How we research: editorial standards.

Frequently asked

What is the status of Fraser River Tunnel (George Massey replacement)?

As of October 12, 2026: Early works since Jan 2026; RFQs for first two packages issued June 16, 2026. Next: Package 1–2 contractors selected early 2027; remaining three packages procured in 2027; major construction 2027.

Who is the contractor on Fraser River Tunnel (George Massey replacement)?

Re-procuring; the Cross Fraser Partnership early-works agreement was terminated in 2026. Owner: Province of B.C. (Ministry of Transportation and Transit).

How much does Fraser River Tunnel (George Massey replacement) cost?

C$8.5B (Province); Canada up to C$3B.

What is the timeline for Fraser River Tunnel (George Massey replacement)?

Construction start: early works jan 2026; major 2027; in service: september 2031.

How do suppliers register for Fraser River Tunnel (George Massey replacement)?

Through the owner's supplier page: https://bcbid.gov.bc.ca/. Public-sector packages in British Columbia are also posted on the provincial tender portal.