Guide · updated October 12, 2026
LNG projects in Canada: status, cost and timeline (2026)
Every LNG export project on Canada’s West Coast, from LNG Canada Phase 2 to Woodfibre, Cedar and Ksi Lisims, with investment-decision status, cost, contractors and in-service dates, from owner and government sources.
Canada’s West Coast LNG has moved from one project to a cluster. LNG Canada Phase 2 took its investment decision in September 2026 and Coastal GasLink Phase 2 followed. Cedar and Woodfibre are under construction. Ksi Lisims and its Prince Rupert Gas Transmission line are targeting a decision by the end of 2026. In the Lower Mainland, FortisBC’s Tilbury expansion is the domestic-supply play.
In this guide
- LNG Canada Phase 2
- Coastal GasLink Phase 2
- Cedar LNG
- Ksi Lisims LNG + Prince Rupert Gas Transmission (PRGT)
- Woodfibre LNG
- Tilbury Phase 2 LNG
LNG Canada Phase 2
British Columbia · LNG · Kitimat
LNG Canada Phase 2 starts early works three days after its investment decision.
- Status: FID Sep 28, 2026; early works since Oct 1
- Next: ~4 months of early works, then full construction
- Disclosed cost: ~C$33B private investment (federal estimate)
- Owner: LNG Canada JV: Shell, PETRONAS, PetroChina, Mitsubishi, KOGAS; Contractors: JGC Fluor BC LNG II JV
Sources:
Coastal GasLink Phase 2
British Columbia · Pipeline · Dawson Creek–Kitimat
Coastal GasLink Phase 2 is a compressor-station job, not a pipeline spread.
- Status: Proceeding; conditions met Sep 29
- Next: Construction early 2027; in service early 2030s
- Disclosed cost: Not publicly disclosed
- Owner: Coastal GasLink; operated by TC Energy; Contractors: LNG Canada (Phase 2 Execution Manager)
- In service: Early 2030s
Sources:
Cedar LNG
British Columbia · LNG · Kitimat
Cedar LNG: site crews hand over as the floating plant takes shape in Korea.
- Status: Pipeline welded; FLNG >50%
- Next: Ledcor handover Oct 2026; startup late 2028
- Disclosed cost: US$4.0B total (US$3.4B capital)
- Owner: Haisla Nation and Pembina; Contractors: Ledcor Haisla LP; FLNG by Samsung Heavy Industries
- In service: Late 2028
Sources:
Ksi Lisims LNG + Prince Rupert Gas Transmission (PRGT)
British Columbia · LNG + pipeline · North Coast
Ksi Lisims has 9 of 12 Mtpa lined up as its FID deadline nears.
- Status: Pre-FID
- Next: FID targeted by end-2026; construction early 2027 if approved
- Disclosed cost: C$30B facility (federal 2026 figure) + C$10–12B PRGT
- Owner: Nisga'a Nation, Rockies LNG, Western LNG; Contractors: PRGT: Surerus Murphy JV (onshore), Allseas (subsea)
- In service: 2032 (first Uniper deliveries)
Sources:
Woodfibre LNG
British Columbia · LNG · Squamish
Woodfibre LNG: all 16 modules on site, tunnel holed through.
- Status: ~65% complete
- Next: Pipe installation in tunnel; first cargo targeted Dec 2027
- Disclosed cost: US$8.8B
- Owner: Woodfibre LNG; feed pipeline by FortisBC
- In service: End of 2027
Sources:
Tilbury Phase 2 LNG
British Columbia · LNG · Delta
Tilbury Phase 2: approved by both governments, not yet sanctioned.
- Status: B.C. EA certificate and federal decision, both Sep 21
- Next: Remaining permits; owner investment decision
- Disclosed cost: C$3.1B (FortisBC projection)
- Owner: FortisBC Holdings
- In service: Six-year build
Sources:
Frequently asked
How many LNG export projects are under construction in Canada?
LNG Canada (Phase 1 operating, Phase 2 in early works), Cedar LNG and Woodfibre LNG are under construction. Ksi Lisims LNG has its approvals and is targeting a final investment decision.
When will LNG Canada Phase 2 be completed?
The owners have not published an in-service date. Early works began on October 1, 2026, after the September 28 investment decision.
The full brief is in the October 2026 report: the procurement packages to watch, the buyer and contractor contacts, the dates on the 90-day calendar and how this project ties into the rest of the pipeline.
Read it for C$299 a year or see a free sample