Major projects coming into service in 2028

7 dated milestones across 7 tracked projects in B.C., Alberta and Saskatchewan.

WhenTypeProjectWhat happensBuyer
Back half of 2028In serviceMeta data centre, Sturgeon CountyMeta load in serviceMeta / Capital Power
Oct 2028In serviceBC Hydro Peace to Kelly Lake Stations SustainmentPeace to Kelly Lake stations work in serviceBC Hydro
End of 2028In serviceShell Polaris CCS and Atlas hubPolaris operationsShell
Late 2028In serviceCedar LNGCedar LNG startupCedar LNG Partners
Late 2028In serviceEnbridge Sunrise Expansion ProgramSunrise Expansion in serviceEnbridge (Westcoast)
Q4 2028In serviceCenovus Christina Lake interconnectStartupCenovus
Q4 2028In serviceArtemis Gold Blackwater EP2 expansionThroughput reaches 21 MtpaArtemis Gold

Projects on this list

ProjectProvinceOwnerContractorsStatusNext milestoneDisclosed cost
Meta data centre, Sturgeon CountyAlbertaMeta Platforms—Ground broken Jul 8, 2026Load in service back half of 2028>C$13B
BC Hydro Peace to Kelly Lake Stations SustainmentB.C.BC Hydro—Implementation phase (board-approved Dec 2022); no material changes in the Nov 2024–Oct 2025 reporting periodIn service October 2028C$354.0M authorized (BC Hydro)
Shell Polaris CCS and Atlas hubAlbertaShell Canada (Polaris 100%); Atlas hub 50/50 with ATCO EnPower—Under construction (Alberta Major Projects); Shell projected a peak of about 400 workers in Q4 2025–Q1 2026Operations toward the end of 2028Not publicly disclosed
Cedar LNGB.C.Haisla Nation and PembinaLedcor Haisla LP; FLNG by Samsung Heavy IndustriesPipeline welded; FLNG >50%Ledcor handover Oct 2026; startup late 2028US$4.0B total (US$3.4B capital)
Enbridge Sunrise Expansion ProgramB.C.Westcoast Energy (Enbridge)—Federal approval April 2026; construction began July 2026Construction Q3 2026–Q4 2028; in service late 2028C$4B (Enbridge)
Cenovus Christina Lake interconnectAlbertaCenovus (including former MEG assets)—AER notice Sep 15Statement-of-concern deadline Oct 15; construction mid-2027; startup Q4 2028Not publicly disclosed
Artemis Gold Blackwater EP2 expansionB.C.Artemis GoldEPCM: LycopodiumMajor works construction under way since Aug 2026; on budgetThroughput to 21 Mtpa by Q4 2028C$1.44B (EP2, company)

Full bid calendar · All stage and milestone pages

What subscribers see that this page doesn’t show

What you getFreePaid
Project list with owner, status, next milestone and cost✓✓
Next 10 dates on the bid calendar✓✓
All 64 dated milestones, .ics export and a watchlist—✓
What happens on each date (details for every milestone)—✓
Procurement packages and buyer contacts per project—✓
Two monthly reports (PDF) with maps and buyer tables—✓
Mid-month update on projects that moved—✓

Upgrade now: C$299/yr or C$39 a month

Opens secure checkout (card, Apple Pay, Google Pay, Link). Cancel any time in two clicks.