Explainer

How the B.C. Environmental Assessment Office (EAO) process works

Large projects in British Columbia (mines, LNG plants, pipelines, transmission lines and other major industrial projects above set size thresholds) need an environmental assessment certificate from the province before they can be built. The Environmental Assessment Office (EAO) runs the review under the Environmental Assessment Act (2018).

The main stages

  1. Early engagement: the proponent describes the project, and the EAO consults Indigenous nations, the public and agencies.
  2. Readiness decision: the EAO decides whether the project goes into a full assessment.
  3. Process planning: the scope, methods and timelines are set.
  4. Application development and review: the proponent submits its application, and it is reviewed.
  5. Effects assessment and recommendation: the EAO prepares its assessment report and draft conditions.
  6. Decision: provincial ministers decide whether to issue a certificate, with conditions.

After the certificate

A certificate has a deadline by which the project must be substantially started, or it expires. The EAO can make, and reconsider, a substantially-started designation. That is happening now on Seabridge KSM. Many projects also need a federal decision, and these can run in parallel or under a cooperation agreement, as on Tilbury Phase 2 LNG.

Tracked B.C. projects with EAO files

What subscribers see that this page doesn’t show

What you getFreePaid
Project list with owner, status, next milestone and cost✓✓
Next 10 dates on the bid calendar✓✓
All 64 dated milestones, .ics export and a watchlist—✓
What happens on each date (details for every milestone)—✓
Procurement packages and buyer contacts per project—✓
Two monthly reports (PDF) with maps and buyer tables—✓
Mid-month update on projects that moved—✓

Upgrade now: C$299/yr or C$39 a month

Opens secure checkout (card, Apple Pay, Google Pay, Link). Cancel any time in two clicks.