Guide · updated October 12, 2026
Alberta data-centre projects: who is building, where, and the power behind them
The AI and hyperscale data-centre projects proposed and under way in Alberta and the rest of Western Canada, with owner, power source, status and disclosed cost.
Alberta has the largest pipeline of AI data-centre proposals in Canada, because it has cheap gas, a deregulated power market and room to build. Interconnection has a cap, though. The projects most likely to be built bring their own power or have a signed utility supply deal, like Meta and Capital Power. Every project below links to the owner or regulator filing behind it.
In this guide
- Meta data centre, Sturgeon County
- Greenlight Electricity Centre
- Capital Power supply to Meta / Genesee
- Keephills data centre (TransAlta)
- Beacon AI Centers (Heartland and Indus)
- Wonder Valley data centre
- Bell AI Fabric Hillside AI Centre, Kamloops
- Bell AI Fabric, Regina area
- eStruxture CAL-3 data centre
- TNE / Data District data centres (Phase 1)
- Crusoe AI data centres with Kalina gas power
Meta data centre, Sturgeon County
Alberta · Data centre · Sturgeon County
Meta's first Canadian data centre: 1 GW, >C$13B, under way.
- Status: Ground broken Jul 8, 2026
- Next: Load in service back half of 2028
- Disclosed cost: >C$13B
- Owner: Meta Platforms
- In service: Back half of 2028
Sources:
Greenlight Electricity Centre
Alberta · Gas power · Sturgeon County
Greenlight Electricity Centre: Alberta's first dedicated data-centre power plant.
- Status: FID Jul 2; all major approvals in hand
- Next: In service H2 2030
- Disclosed cost: ~C$4.6B incl. financing
- Owner: Pembina 47.5% · Morgan Stanley Infrastructure 47.5% · Kineticor 5%; Contractors: Aecon + Técnicas Reunidas (fixed price) · Siemens Energy
- In service: H2 2030
Sources:
Capital Power supply to Meta / Genesee
Alberta · Power supply · Edmonton
Capital Power bridges Meta to 2030 and pitches Genesee to the next hyperscaler.
- Status: —
- Next: Load in back half of 2028
- Disclosed cost: Not publicly disclosed
- Owner: Meta Platforms
- In service: Back half of 2028
Sources:
Keephills data centre (TransAlta)
Alberta · Data centre · Parkland County
Keephills: an AESO allocation in hand, but no binding deal yet.
- Status: Non-binding MOU, Feb 27, 2026
- Next: Definitive agreements and a ~230 MW PPA
- Disclosed cost: Not publicly disclosed
- Owner: TransAlta (site and power) · CPP Investments and Brookfield
Sources:
Beacon AI Centers (Heartland and Indus)
Alberta · Data centre + gas · Heartland
Beacon AI Centers waits on the AUC for two gas plants.
- Status: —
- Next: AUC decisions
- Disclosed cost: Up to US$7.2B across the Alberta portfolio
Sources:
Wonder Valley data centre
Alberta · Data centre · MD of Greenview
Wonder Valley: zoning help, but no permits yet.
- Status: Proposed; EPEA and Water Act approvals outstanding
- Next: Permit applications and decisions
- Disclosed cost: Proponent claims ~C$70B at full build
Sources:
Bell AI Fabric Hillside AI Centre, Kamloops
British Columbia · Data centre · Kamloops
Bell AI Fabric's Hillside AI Centre at TRU is under construction.
- Status: Construction since spring 2026
- Next: Completion late 2027
- Disclosed cost: Not publicly disclosed
- Owner: Bell AI Fabric (with TRU Community Trust)
- In service: Late 2027
Sources:
Bell AI Fabric, Regina area
Saskatchewan · Data centre + gas · Regina area
Bell AI Fabric: 300 MW under construction, with a path to 1.2 GW.
- Status: 300 MW under construction (RM of Sherwood); +900 MW non-binding MOU
- Next: Tenant commitments, a power partner, EAs
- Disclosed cost: ~C$1.7B for the 300 MW phase; >C$50B for the 1.2 GW expansion (provincial figure)
- Owner: Bell Canada
Sources:
eStruxture CAL-3 data centre
Alberta · Data centre · Rocky View County (Calgary)
Alberta's largest colocation build: a 90 MW, Tier III, C$750M AI-ready campus.
- Status: Under construction (Alberta Major Projects, 2024–2026)
- Next: Phase 1 online in 2026
- Disclosed cost: C$750M (Alberta Major Projects)
- Owner: eStruxture
- In service: 2026
Sources:
TNE / Data District data centres (Phase 1)
Alberta · Data centre · Olds, Bonnyville, Calgary and Edmonton regions
Four data centres totalling 240 MW and C$1.26B; Olds first in 2026.
- Status: Proposed (Alberta Major Projects)
- Next: Olds construction 2026; Bonnyville 2027
- Disclosed cost: C$1.26B (four sites)
- Owner: Technologies New Energy and Data District
Sources:
Crusoe AI data centres with Kalina gas power
Alberta · Data centre · Brazeau, Red Deer and Rocky View counties
Crusoe plans gas-powered AI campuses at 170 MW Kalina energy parks, C$3B in total.
- Status: Proposed (Alberta Major Projects)
- Next: Power plant and site approvals
- Disclosed cost: C$3B (about C$1B per 170 MW plant)
- Owner: Crusoe (power: Kalina Distributed Power)
Sources:
Frequently asked
Why are data centres being built in Alberta?
Natural gas for on-site power, a cold climate, available land and a deregulated electricity market. Grid connection limits mean many projects plan their own generation.
What is the largest data-centre project in Alberta?
By disclosed figures, Meta’s campus in Sturgeon County (C$13B+). Wonder Valley has the largest proposed power footprint but no disclosed construction cost.
The full brief is in the October 2026 report: the procurement packages to watch, the buyer and contractor contacts, the dates on the 90-day calendar and how this project ties into the rest of the pipeline.