Region · updated October 12, 2026

Major projects in British Columbia

24 tracked projects. LNG on the north coast and the Fraser, the North Coast Transmission Line, and the mines feeding off new power in the northwest.

ProjectProvinceSectorStatusNext milestoneDisclosed cost
LNG Canada Phase 2B.C.LNGFID Sep 28, 2026; early works since Oct 1~4 months of early works, then full construction~C$33B private investment (federal estimate)
Coastal GasLink Phase 2B.C.PipelineProceeding; conditions met Sep 29Construction early 2027; in service early 2030s—
Cedar LNGB.C.LNGPipeline welded; FLNG >50%Ledcor handover Oct 2026; startup late 2028US$4.0B total (US$3.4B capital)
Ksi Lisims LNG + Prince Rupert Gas Transmission (PRGT)B.C.LNG + pipelinePre-FIDFID targeted by end-2026; construction early 2027 if approvedC$30B facility (federal 2026 figure) + C$10–12B PRGT
Woodfibre LNGB.C.LNG~65% completePipe installation in tunnel; first cargo targeted Dec 2027US$8.8B
North Coast Transmission Line (NCTL)B.C.PowerPhase 1 clearing since July; four line teams shortlistedOct 15 final draft contract · Dec 15 proposals · May 2027 awardC$6B (Phases 1–2, BC Hydro estimate); C$3.9B federal–provincial commitment
Tilbury Phase 2 LNGB.C.LNGB.C. EA certificate and federal decision, both Sep 21Remaining permits; owner investment decisionC$3.1B (FortisBC projection)
Red Chris block cave and Eskay CreekB.C.Mining—Red Chris FID later this year · Eskay power late Nov, first ore Q2 2027Red Chris ~C$3B (Newmont); Eskay Creek US$659M (2026 update)
Bell AI Fabric Hillside AI Centre, KamloopsB.C.Data centreConstruction since spring 2026Completion late 2027—
Surrey Langley SkyTrainB.C.TransitAll eight stations under construction (May 2026); C$2.8B spent to July 2026Initial testing from late 2026; construction along the corridor through 2029C$5.996B (provincial budget)
Broadway SubwayB.C.TransitAll trackwork complete (Sept 2026); dynamic train testing since May 2026Broadway fully reopens Jan 2027; trial running then opening in fall 2027Nearly C$3B (Province); B.C. C$1.957B, Canada C$896.9M, Vancouver C$100.3M in kind
Fraser River Tunnel (George Massey replacement)B.C.TransportationEarly works since Jan 2026; RFQs for first two packages issued June 16, 2026Package 1–2 contractors selected early 2027; remaining three packages procured in 2027; major construction 2027C$8.5B (Province); Canada up to C$3B
Seabridge KSM copper-gold projectB.C.MiningTreaty Creek Terminal substantially complete and energized Aug 27, 2026; EAO reconsideration of substantially-started designation under wayTerminal in service by Nov 2026; EAO recommendation on renewed determinationOver C$1.2B invested to date (company)
Site C Clean Energy ProjectB.C.PowerAll six generating units in service by Aug 8, 2025; more than 94% complete overall (Mar 2026)Remaining works and close-out; about C$1.1B left to spendC$16B approved budget (C$14.9B spent to Mar 31, 2026)
Trans Mountain optimization (DRA and Mainline Optimization Project)B.C.PipelineDrag Reducing Agent project under construction; Mainline Optimization Project application filed with the CERCER review of the MOP; both projects subject to final investment decisions—
Eagle Mountain–Woodfibre Gas Pipeline (EGP)B.C.PipelineTunnel breakthrough Sept 2026; pipeline testing in Squamish from Oct 2026Pipeline installation in the tunnel; all components complete in 2026, restoration in 2027—
Enbridge Sunrise Expansion ProgramB.C.PipelineFederal approval April 2026; construction began July 2026Construction Q3 2026–Q4 2028; in service late 2028C$4B (Enbridge)
AltaGas REEF (Ridley Island Energy Export Facility)B.C.LPG export terminal85% complete (Q2 2026); marine works slowed by weatherOnline before end of March 2027~C$1.5B (revised, up 12%)
Teck Highland Valley Copper Mine Life ExtensionB.C.MiningUnder construction since Aug 2025; mill upgrades advancing in H2 2026Construction through 2028C$2.1–2.4B (Teck)
Roberts Bank Terminal 2B.C.PortsPreferred proponent named July 2026; design and early-works agreement expected Q3 2026Design-build agreement expected Q1 2028, then construction; completion mid-2030s—
Artemis Gold Blackwater EP2 expansionB.C.MiningMajor works construction under way since Aug 2026; on budgetThroughput to 21 Mtpa by Q4 2028C$1.44B (EP2, company)
Centerra Kemess restartB.C.MiningPEA (Jan 2026): after-tax NPV5% C$1.1B; pre-feasibility study expected 2027Pre-feasibility 2027; BC Hydro substation upgrade and permits on the critical path—
BC Hydro 2024 and 2025 calls for powerB.C.Power2024 call: 10 EPAs (nine wind, one solar), about 4,830 GWh/yr. 2025 call: four projects, about 3,500 GWh/yr, announced May 2026Permitting; BC Hydro interconnection work from 2027; projects online from 2030–2033C$4.3B private investment (2025 call, Province)
BC Hydro Peace to Kelly Lake Stations SustainmentB.C.PowerImplementation phase (board-approved Dec 2022); no material changes in the Nov 2024–Oct 2025 reporting periodIn service October 2028C$354.0M authorized (BC Hydro)

See all 50 tracked projects

The full brief is in the October 2026 report: the procurement packages to watch, the buyer and contractor contacts, the dates on the 90-day calendar and how this project ties into the rest of the pipeline.

Read it for C$299 a year or see a free sample

Cancel any time in two clicks.