Project stage · updated October 12, 2026
B.C. major projects under construction in 2026
13 tracked projects, C$65B+ in disclosed Canadian-dollar cost. Projects with construction or early works under way in British Columbia, with the contractor teams we have on record.
| Project | Province | Owner | Contractors | Status | Next milestone | Disclosed cost |
|---|---|---|---|---|---|---|
| LNG Canada Phase 2 | B.C. | LNG Canada JV: Shell, PETRONAS, PetroChina, Mitsubishi, KOGAS | JGC Fluor BC LNG II JV | FID Sep 28, 2026; early works since Oct 1 | ~4 months of early works, then full construction | ~C$33B private investment (federal estimate) |
| Cedar LNG | B.C. | Haisla Nation and Pembina | Ledcor Haisla LP; FLNG by Samsung Heavy Industries | Pipeline welded; FLNG >50% | Ledcor handover Oct 2026; startup late 2028 | US$4.0B total (US$3.4B capital) |
| Woodfibre LNG | B.C. | Woodfibre LNG; feed pipeline by FortisBC | — | ~65% complete | Pipe installation in tunnel; first cargo targeted Dec 2027 | US$8.8B |
| North Coast Transmission Line (NCTL) | B.C. | BC Hydro (500 kV) | — | Phase 1 clearing since July; four line teams shortlisted | Oct 15 final draft contract · Dec 15 proposals · May 2027 award | C$6B (Phases 1–2, BC Hydro estimate); C$3.9B federal–provincial commitment |
| Surrey Langley SkyTrain | B.C. | Province of B.C. (TI Corp delivers) | Guideway: SkyLink Guideway Partners (Dragados Canada, Ledcor). Stations: South Fraser Station Partners (Aecon, Acciona, Pomerleau). Systems and trackwork: Transit Integrators BC (AtkinsRéalis, Western Pacific Enterprises) | All eight stations under construction (May 2026); C$2.8B spent to July 2026 | Initial testing from late 2026; construction along the corridor through 2029 | C$5.996B (provincial budget) |
| Broadway Subway | B.C. | Province of B.C. | — | All trackwork complete (Sept 2026); dynamic train testing since May 2026 | Broadway fully reopens Jan 2027; trial running then opening in fall 2027 | Nearly C$3B (Province); B.C. C$1.957B, Canada C$896.9M, Vancouver C$100.3M in kind |
| Fraser River Tunnel (George Massey replacement) | B.C. | Province of B.C. (Ministry of Transportation and Transit) | Re-procuring; the Cross Fraser Partnership early-works agreement was terminated in 2026 | Early works since Jan 2026; RFQs for first two packages issued June 16, 2026 | Package 1–2 contractors selected early 2027; remaining three packages procured in 2027; major construction 2027 | C$8.5B (Province); Canada up to C$3B |
| Eagle Mountain–Woodfibre Gas Pipeline (EGP) | B.C. | FortisBC | Tunnel: Frontier-Kemper Michels JV | Tunnel breakthrough Sept 2026; pipeline testing in Squamish from Oct 2026 | Pipeline installation in the tunnel; all components complete in 2026, restoration in 2027 | Not publicly disclosed |
| Enbridge Sunrise Expansion Program | B.C. | Westcoast Energy (Enbridge) | — | Federal approval April 2026; construction began July 2026 | Construction Q3 2026–Q4 2028; in service late 2028 | C$4B (Enbridge) |
| AltaGas REEF (Ridley Island Energy Export Facility) | B.C. | AltaGas (with Royal Vopak) | — | About 85% complete (Q2 2026); onshore equipment over 90% installed, rail utility corridor 80%; 1.2 km jetty slowed by weather and marine-mammal measures | Online before end of March 2027 | About C$1.5B gross (raised 12% from C$1.35B) |
| Teck Highland Valley Copper Mine Life Extension | B.C. | Teck Resources (100%) | — | Under construction since Aug 2025; mill upgrades advancing in H2 2026 | Construction through 2028 | C$2.1–2.4B (Teck) |
| Artemis Gold Blackwater EP2 expansion | B.C. | Artemis Gold | EPCM: Lycopodium | Major works construction under way since Aug 2026; on budget | Throughput to 21 Mtpa by Q4 2028 | C$1.44B (EP2, company) |
| Bell AI Fabric Hillside AI Centre, Kamloops | B.C. | Bell AI Fabric (with TRU Community Trust) | — | Construction since spring 2026 | Completion late 2027 | Not publicly disclosed |
Next dates on these projects
| When | Type | Project | What happens | Buyer |
|---|---|---|---|---|
| Oct 15 | Tender / RFP | North Coast Transmission Line (NCTL) | Prince George–Glenannan final draft contract issued to the four shortlisted line teams | BC Hydro |
| Oct 2026 | Award | North Coast Transmission Line (NCTL) | Steel structures and optical ground wire awards; camp healthcare RFP | BC Hydro |
| Oct 2026 | Construction | Cedar LNG | Ledcor hands over the site works | Cedar LNG Partners |
| Oct 2026 | Construction | Eagle Mountain–Woodfibre Gas Pipeline (EGP) | Pipeline testing in Squamish | FortisBC |
| Nov 2026 | Award | North Coast Transmission Line (NCTL) | Segment G clearing award | BC Hydro |
| Dec 15, 2026 | Tender / RFP | North Coast Transmission Line (NCTL) | Prince George–Glenannan line proposals due | BC Hydro |
| Dec 2026 | Award | North Coast Transmission Line (NCTL) | Series capacitor bank award | BC Hydro |
| Dec 2026 | Construction | North Coast Transmission Line (NCTL) | Line relocation work starts between Williston and Beverley | BC Hydro |
| Late 2026 | Construction | Eagle Mountain–Woodfibre Gas Pipeline (EGP) | Hydrostatic testing of the new pipeline section | FortisBC |
| Early 2027 | Construction | LNG Canada Phase 2 | Early works move to full construction (about four months after Oct 1) | JGC Fluor BC LNG II JV |
All 50 projects · Bid calendar · All stage and milestone pages
What subscribers see that this page doesn’t show
| What you get | Free | Paid |
|---|---|---|
| Project list with owner, status, next milestone and cost | ✓ | ✓ |
| Next 10 dates on the bid calendar | ✓ | ✓ |
| All 64 dated milestones, .ics export and a watchlist | — | ✓ |
| What happens on each date (details for every milestone) | — | ✓ |
| Procurement packages and buyer contacts per project | — | ✓ |
| Two monthly reports (PDF) with maps and buyer tables | — | ✓ |
| Mid-month update on projects that moved | — | ✓ |
Upgrade now: C$299/yr or C$39 a month
Opens secure checkout (card, Apple Pay, Google Pay, Link). Cancel any time in two clicks.
Frequently asked
Which projects are on this list?
LNG Canada Phase 2, Cedar LNG, Woodfibre LNG, North Coast Transmission Line (NCTL), Surrey Langley SkyTrain, Broadway Subway, Fraser River Tunnel (George Massey replacement), Eagle Mountain–Woodfibre Gas Pipeline (EGP), Enbridge Sunrise Expansion Program, AltaGas REEF (Ridley Island Energy Export Facility), Teck Highland Valley Copper Mine Life Extension, Artemis Gold Blackwater EP2 expansion, Bell AI Fabric Hillside AI Centre, Kamloops.
How is the stage decided?
From the status the owner, regulator or government has published as of October 12, 2026. Each project page lists its sources.