Project stage · updated October 12, 2026

B.C. major projects under construction in 2026

13 tracked projects, C$65B+ in disclosed Canadian-dollar cost. Projects with construction or early works under way in British Columbia, with the contractor teams we have on record.

ProjectProvinceOwnerContractorsStatusNext milestoneDisclosed cost
LNG Canada Phase 2B.C.LNG Canada JV: Shell, PETRONAS, PetroChina, Mitsubishi, KOGASJGC Fluor BC LNG II JVFID Sep 28, 2026; early works since Oct 1~4 months of early works, then full construction~C$33B private investment (federal estimate)
Cedar LNGB.C.Haisla Nation and PembinaLedcor Haisla LP; FLNG by Samsung Heavy IndustriesPipeline welded; FLNG >50%Ledcor handover Oct 2026; startup late 2028US$4.0B total (US$3.4B capital)
Woodfibre LNGB.C.Woodfibre LNG; feed pipeline by FortisBC—~65% completePipe installation in tunnel; first cargo targeted Dec 2027US$8.8B
North Coast Transmission Line (NCTL)B.C.BC Hydro (500 kV)—Phase 1 clearing since July; four line teams shortlistedOct 15 final draft contract · Dec 15 proposals · May 2027 awardC$6B (Phases 1–2, BC Hydro estimate); C$3.9B federal–provincial commitment
Surrey Langley SkyTrainB.C.Province of B.C. (TI Corp delivers)Guideway: SkyLink Guideway Partners (Dragados Canada, Ledcor). Stations: South Fraser Station Partners (Aecon, Acciona, Pomerleau). Systems and trackwork: Transit Integrators BC (AtkinsRéalis, Western Pacific Enterprises)All eight stations under construction (May 2026); C$2.8B spent to July 2026Initial testing from late 2026; construction along the corridor through 2029C$5.996B (provincial budget)
Broadway SubwayB.C.Province of B.C.—All trackwork complete (Sept 2026); dynamic train testing since May 2026Broadway fully reopens Jan 2027; trial running then opening in fall 2027Nearly C$3B (Province); B.C. C$1.957B, Canada C$896.9M, Vancouver C$100.3M in kind
Fraser River Tunnel (George Massey replacement)B.C.Province of B.C. (Ministry of Transportation and Transit)Re-procuring; the Cross Fraser Partnership early-works agreement was terminated in 2026Early works since Jan 2026; RFQs for first two packages issued June 16, 2026Package 1–2 contractors selected early 2027; remaining three packages procured in 2027; major construction 2027C$8.5B (Province); Canada up to C$3B
Eagle Mountain–Woodfibre Gas Pipeline (EGP)B.C.FortisBCTunnel: Frontier-Kemper Michels JVTunnel breakthrough Sept 2026; pipeline testing in Squamish from Oct 2026Pipeline installation in the tunnel; all components complete in 2026, restoration in 2027Not publicly disclosed
Enbridge Sunrise Expansion ProgramB.C.Westcoast Energy (Enbridge)—Federal approval April 2026; construction began July 2026Construction Q3 2026–Q4 2028; in service late 2028C$4B (Enbridge)
AltaGas REEF (Ridley Island Energy Export Facility)B.C.AltaGas (with Royal Vopak)—About 85% complete (Q2 2026); onshore equipment over 90% installed, rail utility corridor 80%; 1.2 km jetty slowed by weather and marine-mammal measuresOnline before end of March 2027About C$1.5B gross (raised 12% from C$1.35B)
Teck Highland Valley Copper Mine Life ExtensionB.C.Teck Resources (100%)—Under construction since Aug 2025; mill upgrades advancing in H2 2026Construction through 2028C$2.1–2.4B (Teck)
Artemis Gold Blackwater EP2 expansionB.C.Artemis GoldEPCM: LycopodiumMajor works construction under way since Aug 2026; on budgetThroughput to 21 Mtpa by Q4 2028C$1.44B (EP2, company)
Bell AI Fabric Hillside AI Centre, KamloopsB.C.Bell AI Fabric (with TRU Community Trust)—Construction since spring 2026Completion late 2027Not publicly disclosed

Next dates on these projects

WhenTypeProjectWhat happensBuyer
Oct 15Tender / RFPNorth Coast Transmission Line (NCTL)Prince George–Glenannan final draft contract issued to the four shortlisted line teamsBC Hydro
Oct 2026AwardNorth Coast Transmission Line (NCTL)Steel structures and optical ground wire awards; camp healthcare RFPBC Hydro
Oct 2026ConstructionCedar LNGLedcor hands over the site worksCedar LNG Partners
Oct 2026ConstructionEagle Mountain–Woodfibre Gas Pipeline (EGP)Pipeline testing in SquamishFortisBC
Nov 2026AwardNorth Coast Transmission Line (NCTL)Segment G clearing awardBC Hydro
Dec 15, 2026Tender / RFPNorth Coast Transmission Line (NCTL)Prince George–Glenannan line proposals dueBC Hydro
Dec 2026AwardNorth Coast Transmission Line (NCTL)Series capacitor bank awardBC Hydro
Dec 2026ConstructionNorth Coast Transmission Line (NCTL)Line relocation work starts between Williston and BeverleyBC Hydro
Late 2026ConstructionEagle Mountain–Woodfibre Gas Pipeline (EGP)Hydrostatic testing of the new pipeline sectionFortisBC
Early 2027ConstructionLNG Canada Phase 2Early works move to full construction (about four months after Oct 1)JGC Fluor BC LNG II JV

All 50 projects · Bid calendar · All stage and milestone pages

What subscribers see that this page doesn’t show

What you getFreePaid
Project list with owner, status, next milestone and cost✓✓
Next 10 dates on the bid calendar✓✓
All 64 dated milestones, .ics export and a watchlist—✓
What happens on each date (details for every milestone)—✓
Procurement packages and buyer contacts per project—✓
Two monthly reports (PDF) with maps and buyer tables—✓
Mid-month update on projects that moved—✓

Upgrade now: C$299/yr or C$39 a month

Opens secure checkout (card, Apple Pay, Google Pay, Link). Cancel any time in two clicks.

Frequently asked

Which projects are on this list?

LNG Canada Phase 2, Cedar LNG, Woodfibre LNG, North Coast Transmission Line (NCTL), Surrey Langley SkyTrain, Broadway Subway, Fraser River Tunnel (George Massey replacement), Eagle Mountain–Woodfibre Gas Pipeline (EGP), Enbridge Sunrise Expansion Program, AltaGas REEF (Ridley Island Energy Export Facility), Teck Highland Valley Copper Mine Life Extension, Artemis Gold Blackwater EP2 expansion, Bell AI Fabric Hillside AI Centre, Kamloops.

How is the stage decided?

From the status the owner, regulator or government has published as of October 12, 2026. Each project page lists its sources.