Milestones · updated October 12, 2026

Upcoming regulatory deadlines and investment decisions

10 dated milestones across 10 tracked projects in B.C., Alberta and Saskatchewan. The first 4 are shown in full; subscribers see every detail.

WhenTypeProjectWhat happensBuyer
Oct 15RegulatoryCenovus Christina Lake interconnectAER statement-of-concern deadlineCenovus / AER
Nov 2026DecisionCanadian Natural growth projects (on hold)Oil Sands Alliance–Alberta–federal agreements targetedCanadian Natural
Nov–Dec 2026RegulatoryBeacon AI Centers (Heartland and Indus)AUC decisions on Beacon Heartland (proceeding 30518) and IndusAUC
By end-2026DecisionKsi Lisims LNG + Prince Rupert Gas Transmission (PRGT)Ksi Lisims FID targeted (expected, not confirmed)Ksi Lisims LNG
WhenTypeProjectWhat happensBuyer
By end-2026DecisionRed Chris block cave and Eskay CreekSubscribers onlyNewmont / Imperial Metals
Dec 2026RegulatoryWonder Valley data centreSubscribers onlyMD of Greenview / O'Leary Digital
Coming months (expected)RegulatoryKeephills data centre (TransAlta)Subscribers onlyBrookfield / CPP Investments
Early 2027 (expected)RegulatoryPacific Link oil pipelineSubscribers onlyAlberta / Trans Mountain / Pembina
2027DecisionCenterra Kemess restartSubscribers onlyCenterra Gold
Late 2027 (target)DecisionAlliance Heartland Expansion and Pathways CCSSubscribers onlyPathways Alliance

Projects on this list

ProjectProvinceOwnerContractorsStatusNext milestoneDisclosed cost
Cenovus Christina Lake interconnectAlbertaCenovus (including former MEG assets)—AER notice Sep 15Statement-of-concern deadline Oct 15; construction mid-2027; startup Q4 2028Not publicly disclosed
Canadian Natural growth projects (on hold)AlbertaCanadian Natural Resources—On hold until definitive Oil Sands Alliance–Alberta–federal agreements are finalizedAgreements targeted November 2026Not publicly disclosed
Beacon AI Centers (Heartland and Indus)Alberta———AUC decisionsUp to US$7.2B across the Alberta portfolio
Ksi Lisims LNG + Prince Rupert Gas Transmission (PRGT)B.C.Nisga'a Nation, Rockies LNG, Western LNGPRGT: Surerus Murphy JV (onshore), Allseas (subsea)Pre-FIDFID targeted by end-2026; construction early 2027 if approvedC$30B facility (federal 2026 figure) + C$10–12B PRGT
Red Chris block cave and Eskay CreekB.C.———Red Chris FID later this year · Eskay power late Nov, first ore Q2 2027Red Chris ~C$3B (Newmont); Eskay Creek US$659M (2026 update)
Wonder Valley data centreAlberta——Proposed; EPEA and Water Act approvals outstandingPermit applications and decisionsProponent claims ~C$70B at full build
Keephills data centre (TransAlta)AlbertaTransAlta (site and power) · CPP Investments and Brookfield—Non-binding MOU, Feb 27, 2026Definitive agreements and a ~230 MW PPANot publicly disclosed
Pacific Link oil pipelineAlbertaTrans Mountain Corp. and APMC (equal); Pembina 10%, plus up to 10% more at COD—Listed Oct 1 under the Building Canada ActMPO conditions document; earliest start Sep 1, 2027C$35.2–43.7B (preliminary, incl. contingency)
Centerra Kemess restartB.C.Centerra Gold—PEA (Jan 2026): after-tax NPV5% C$1.1B; pre-feasibility study expected 2027Pre-feasibility 2027; BC Hydro substation upgrade and permits on the critical pathNot publicly disclosed
Alliance Heartland Expansion and Pathways CCSAlberta———Alliance construction Apr 2028–Sep 2030 (CER page)Alliance not disclosed; Pathways phase 1 C$20–30B (reported)

Full bid calendar · All stage and milestone pages

What subscribers see that this page doesn’t show

What you getFreePaid
Project list with owner, status, next milestone and cost✓✓
Next 10 dates on the bid calendar✓✓
All 64 dated milestones, .ics export and a watchlist—✓
What happens on each date (details for every milestone)—✓
Procurement packages and buyer contacts per project—✓
Two monthly reports (PDF) with maps and buyer tables—✓
Mid-month update on projects that moved—✓

Upgrade now: C$299/yr or C$39 a month

Opens secure checkout (card, Apple Pay, Google Pay, Link). Cancel any time in two clicks.