Milestones · updated October 12, 2026

Upcoming industrial tenders and contract awards in Western Canada

9 dated milestones across 3 tracked projects in B.C., Alberta and Saskatchewan. The first 4 are shown in full; subscribers see every detail.

WhenTypeProjectWhat happensBuyer
Oct 15Tender / RFPNorth Coast Transmission Line (NCTL)Prince George–Glenannan final draft contract issued to the four shortlisted line teamsBC Hydro
Oct 2026AwardNorth Coast Transmission Line (NCTL)Steel structures and optical ground wire awards; camp healthcare RFPBC Hydro
Nov 2026AwardNorth Coast Transmission Line (NCTL)Segment G clearing awardBC Hydro
Dec 15, 2026Tender / RFPNorth Coast Transmission Line (NCTL)Prince George–Glenannan line proposals dueBC Hydro
WhenTypeProjectWhat happensBuyer
Dec 2026AwardNorth Coast Transmission Line (NCTL)Subscribers onlyBC Hydro
Early 2027AwardFraser River Tunnel (George Massey replacement)Subscribers onlyProvince of B.C. (TIBC)
May 2027AwardNorth Coast Transmission Line (NCTL)Subscribers onlyBC Hydro
2027AwardFraser River Tunnel (George Massey replacement)Subscribers onlyProvince of B.C. (TIBC)
Q1 2028AwardRoberts Bank Terminal 2Subscribers onlyVancouver Fraser Port Authority

Projects on this list

ProjectProvinceOwnerContractorsStatusNext milestoneDisclosed cost
North Coast Transmission Line (NCTL)B.C.BC Hydro (500 kV)—Phase 1 clearing since July; four line teams shortlistedOct 15 final draft contract · Dec 15 proposals · May 2027 awardC$6B (Phases 1–2, BC Hydro estimate); C$3.9B federal–provincial commitment
Fraser River Tunnel (George Massey replacement)B.C.Province of B.C. (Ministry of Transportation and Transit)Re-procuring; the Cross Fraser Partnership early-works agreement was terminated in 2026Early works since Jan 2026; RFQs for first two packages issued June 16, 2026Package 1–2 contractors selected early 2027; remaining three packages procured in 2027; major construction 2027C$8.5B (Province); Canada up to C$3B
Roberts Bank Terminal 2B.C.Vancouver Fraser Port AuthorityTerraMarine: Aecon (30%), FlatironDragados Canada, Van Oord, Carlson Construction Group (preferred proponent, landmass and wharf)Preferred proponent named July 2026; design and early-works agreement expected Q3 2026Design-build agreement expected Q1 2028, then construction; completion mid-2030sNot publicly disclosed

Full bid calendar · All stage and milestone pages

What subscribers see that this page doesn’t show

What you getFreePaid
Project list with owner, status, next milestone and cost✓✓
Next 10 dates on the bid calendar✓✓
All 64 dated milestones, .ics export and a watchlist—✓
What happens on each date (details for every milestone)—✓
Procurement packages and buyer contacts per project—✓
Two monthly reports (PDF) with maps and buyer tables—✓
Mid-month update on projects that moved—✓

Upgrade now: C$299/yr or C$39 a month

Opens secure checkout (card, Apple Pay, Google Pay, Link). Cancel any time in two clicks.