Alberta · checked October 25, 2026

Alberta Major Projects inventory compared with our tracker

The Government of Alberta’s Major Projects map lists projects worth $5 million or more. On October 25, 2026 its active list held 985 projects. We track the 21 largest Alberta projects that drive bid work for contractors and suppliers, and 15 of them appear on Alberta’s list.

How the two compare

FeatureAlberta Major ProjectsThis tracker
Published byGovernment of AlbertaWestern Canada Projects, an independent monthly brief
What it coversPrivate and public projects in Alberta worth $5 million or more, from offices and schools to oil sandsThe largest projects that drive bid work: 21 in Alberta and 52 across B.C., Alberta and Saskatchewan
Size on October 25, 2026985 active projects (501 under construction, 484 proposed)21 Alberta projects
CostsEstimated cost for 553 of the 985, revised when new information appearsValue as published by the owner, regulator or government, or “Not disclosed”
ContractorsNamed for 213 of the 985Contractor teams, next milestones and bid packages, in the subscriber brief
SourcesPublic sources such as news, construction journals, permits and tenders (methodology page)Linked on every project page
What changedA monthly Major Project Updates email of added, started and completed projectsA monthly change log with its own URL each month, and an RSS feed
DownloadCSV, XLSX and KMLCSV under CC BY 4.0
PriceFreeFree tracker and dataset; the brief is C$39 a month or C$299 a year

How Alberta builds its list

  • It relies on public sources: news, construction journals, financial reports, building and development permits, developer and contractor websites and tenders. Government of Alberta projects come from the government itself.
  • It shows projects up to two years before construction starts. Energy projects with longer approvals can appear earlier.
  • Stages are proposed, under construction, completed and cancelled. Costs are recorded in millions of dollars and revised when credible new information appears.
  • The province says the list is not exhaustive and asks readers to verify project details with other sources (methodology).

Our 21 Alberta projects on Alberta’s list

Matched by project name and owner on October 25, 2026. Alberta’s stage and estimate are its own; ours are on each project page with sources.

ProjectOur stageAlberta lists it asAlberta stageAlberta estimate
Pacific Link oil pipelineProposed / pre-FIDPacific Link Pipeline (West Coast Oil Pipeline)Proposed$43.7 billion
Meta data centre, Sturgeon CountyUnder constructionMeta Data CentreUnder Construction$13.0 billion
Calgary Green Line LRT (SE)Under constructionCalgary Green Line LRT, Phase 1Under Construction$6.2 billion
Air Products net-zero hydrogen complexUnder constructionAir Products Hydrogen Production and Liquefaction FacilityUnder Construction$4.6 billion
Greenlight Electricity CentreUnder constructionGreenlight Electricity CentreUnder Construction$4.6 billion
Crusoe AI data centres with Kalina gas powerProposed / pre-FIDNot listed by that name––
ATCO Yellowhead MainlineUnder constructionYellowhead Mainline Natural Gas PipelineUnder Construction$2.9 billion
Valley Line West LRTUnder constructionValley Line West LRTUnder Construction$2.7 billion
TNE / Data District data centres (Phase 1)Proposed / pre-FIDTechnologies New Energy & Data District Data Centres (Phase 1)Proposed$1.3 billion
Scotia Place event centreUnder constructionScotia Place (Calgary Events Centre)Under Construction$1.2 billion
eStruxture CAL-3 data centreUnder constructioneStruxture CAL-3 Data CentreUnder Construction$750 million
Alliance Heartland Expansion and Pathways CCSPlanning and regulatoryNot listed by that name––
Beacon AI Centers (Heartland and Indus)Proposed / pre-FIDBeacon Heartland AI Data Centre Hub
Beacon Indus Data Centre Hub
Proposed
Proposed
No estimate
No estimate
Canadian Natural growth projects (on hold)On holdJackpine Mine Expansion
Pike 2 Greenfield Project
Horizon North Mine Expansion Project
Jackfish Brownfield Expansion
Proposed
Proposed
Proposed
Proposed
$8.2 billion
$2.8 billion
$5.5 billion
$750 million
Capital Power supply to Meta / GeneseePlanning and regulatoryNot listed by that name––
Cenovus Christina Lake interconnectPlanning and regulatoryNot listed by that name––
Dow Path2ZeroUnder constructionDow Fort Saskatchewan Path2Zero ExpansionUnder Construction$10.1 billion
Keephills data centre (TransAlta)Proposed / pre-FIDNot listed by that name––
Shell Polaris CCS and Atlas hubUnder constructionShell Polaris Carbon Capture Project
Atlas Carbon Storage Hub
Under Construction
Under Construction
No estimate
No estimate
Suncor Base Mine Extension (proposed)Proposed / pre-FIDNot listed by that name––
Wonder Valley data centreProposed / pre-FIDWonder Valley AI Data Centre Park (Phase 1)Proposed$12.0 billion

“Not listed by that name” means we found no matching entry on October 25, 2026. Alberta adds projects up to two years before construction, so early-stage projects may appear later. Seasonal maintenance turnarounds are not capital projects, so they are not on Alberta’s list.

Which one to use

  • Alberta Major Projects for breadth: smaller projects, schools, hospitals, housing and municipal work, mapped and downloadable.
  • This tracker for the large industrial, energy and data-centre projects, with sourced owner timing, a monthly change log, owner bid lists, and contractor teams and bid packages for subscribers.

Other places to look

What subscribers see that this page doesn’t

What you getFreePaid
C$299/yr
Top 25 projects PDF, with owner and cost for all 25✓✓
The October 2026 issue in full, as a sample✓✓
Monthly headlines by email✓✓
Project list and pages: owner, province, sector, stage, published value and timing✓✓
Next 10 bid-calendar dates✓✓
Each new monthly brief (next one December 3, 2026)–✓
Contractor teams–✓
Status detail, next milestone and dated bid packages–✓
Procurement packages and buyer contacts–✓
Full bid calendar with Outlook and Google export, and the 90-day calendar PDF–✓
Project watchlist–✓
Every issue in your account–✓

C$24.92 a month billed yearly (save 36%), or C$39 a month. Cancel any time in two clicks.

Frequently asked

What is the Alberta Major Projects inventory?

A Government of Alberta map and dataset of private and public projects in Alberta worth $5 million or more. On October 25, 2026 its active list held 985 projects: 501 under construction and 484 proposed.

Does Alberta Major Projects list contractors?

For some projects. On October 25, 2026 it named a contractor for 213 of 985 active projects. Our subscriber brief lists contractor teams, next milestones and bid packages.

How often is Alberta Major Projects updated?

The province revises costs and dates as new information appears and sends a monthly Major Project Updates email of recently added, under-construction and completed projects.

How is this tracker different?

We follow the 52 largest projects in B.C., Alberta and Saskatchewan, publish values only as the owner or regulator states them, link sources on every page and log each month’s changes.